February 2010 -  The first 123 inscribed bricks were installed by skilled brick-layers on the new and extended paved floor of the patio.  Forms were built for pouring the concrete landscape wall, and the fountain was lifted into place.  Preparations for constructing the new deck began.  Plans were drawn for a new gate to connect the patio with the Park.  (Click here to see what came next.) Patio_Project_Update_3.htmlshapeimage_1_link_0
 

9

During a break in the rain, work resumes by Bobcat Excavating & Grading

10

Pathway from parking lot would lead to new patio entrance

11

Larry Carnahan and Dave Bracken check elevations

12

Bob Bundy and Robin Moller review brick pattern with Green Team’s Fred Seddiqi

15

Rigo from Green Team installs brick pavers

14

Eiji Nakamura and son Sean use ancient techniques to lift boulders for fountain

13

Inscribed bricks are laid out, awaiting installation

16

Forms are built for landscape wall adjacent to new turf